Advance curve by physical length in Project 2010

Answered Advance curve by physical length in Project 2010

  • 2012年4月27日 11:28
     
     
    I know that is not the correct way to measure progress but would like to help me in a better applicability in the subject.

    I elaborated on the timeline, without resources, set the duration for their activities;

    Gave 100% increase of the activities and saved to baseline.

    I did an export tool for data analysis (cumulative% completed) and saved the Excel data.

    Zero all advances, determined a status date;

    Display the control table and updated all the activities to date status and repeat the export process to confront the values ​​on a graph.

    The issues are:

    how to generate values ​​close to the percentage (100%) from the date of status?

    How to generate a trend line?

    And if not too much to ask, send me a more efficient procedure for this case. It could be through formulas, VBA ...

    I hope that was clear.

    Thank you.


    Hezequias Vasconcelos

すべての返信

  • 2012年4月27日 20:22
     
     回答済み

    Hello all.

    I found an option in Project 2010 that solves my problem.

    Let the steps:

    1 - With the click Open Project 2010 Project - Reports - Visual Reports.

    2 - Select All - Earned Value Over Time Report.

    3 - Click on View.

    Example of the configuration screen:

    4 - Results obtained.

    Hope this helps others


    Hezequias Vasconcelos