[EPM 2010 - PSI] Actuals updated via a called to project service

回答済み [EPM 2010 - PSI] Actuals updated via a called to project service

  • 2012年3月28日 14:19
     
      コードあり

    Hello,

    Could you please help me on that point ? :)

    I m trying to update an actuals for a specific task:

    My code is:

    backendProject.ProjectDataSet prjDataSet = projectClient.ReadProject(projectId, backendProject.DataStoreEnum.PublishedStore);
    
    backendProject.ProjectDataSet.TaskRow taskActualsUpdated = prjDataSet.Task[15];
    
    taskActualsUpdated.TASK_ACT_WORK = Actuals * 60000;

    After a new select, the actuals has been updated, but i cannot see the correct value in my document. The % Complete is clearly updated (Ex: I have a durartion of 20 MD, I defined an actuals of 40hours -> Percent = 25%) but the value for Work = The total of duration -> 160hours)

    In which column can i see as Project manager, the actuals updated ?


    Math

すべての返信

  • 2012年4月2日 14:23
     
     

    Hi Fix_105,

    I'm not sure about this, but, is it possible that for update task_Act_work, you should update assignments?

    In my idea, the TASK_ACT_WORK value is a sum calculated on assignments actual works.

    Have you any assingments on this task?

    I hope this can helps you,

    Best Regards

    Paolo O.

  • 2012年4月11日 13:34
     
     回答済み

    I was using the correct property. TASK_ACT_WORK contains the actual work (the sum).

    My issue was only linked on the Project center view defined by default. I have found the option to insert additional column in the Task Summary view and now i can see the Actual updated in my document.

    thanks for your support Paolo.


    Math

    • 回答としてマーク Fix_105 2012年4月11日 13:34
    •