Delete microsoft project 2010 standard calendar entry

תשובה Delete microsoft project 2010 standard calendar entry

  • 2012년 5월 11일 금요일 오전 1:44
     
     

    Hi

    I am using a standard calendar.   The calendar has an unkown listing that I would like to delete.   Project will not allow me to delete it keeps hanging up.   It appears to delete until I hit ok to save it.   Any ideas......

모든 응답

  • 2012년 5월 11일 금요일 오전 2:37
     
     답변됨

    Dan,

    When you say "The calendar has an unkown listing..." what exactly are you talking about?  Is it an exception?  Does this happen on all new projects or is it happening on a single file?  If the answer to these are - Yes and on all projects, then the easiest way I can think of is getting another Project 2010 file (preferrably created on a different system) then use the organizer to copy that file's standard calendar into your it into Global.MPT file.  If it is happening on a single file, use the same process, only copy the calendar into that file.  Let us know more details so we can track this issue.

    Hope this helps.


    Gregg D. Richie, PMP, MCTS; Author, Microsoft Project 2010, Microsoft Official Academic Course Series


  • 2012년 5월 11일 금요일 오전 6:02
    중재자
     
     답변됨
    Adding to Gregg, are you connected to Project Server? If yes, then check on if you have permission to edit the Calendar.

    Sapna S