الإجابة Task Update

  • 2012년 5월 10일 목요일 오후 2:29
     
     

    Good morning,

    I have a task "Task A" that I have extended by 5 days.

    ie. Task A     4/9/12    to  5/7/12    was at 40% complete

    the person working on it asked me to give him until the 15 of May.

    So I extended it.

    ie. Task A     4/9/12    to  5/15/12  

    and he said he is 60% complete.

    So when I try to update it to 60% it automatically goes to 100%

    Why is that?  

    project 2010

    task is Fixed Duration and not Effort Driven

    I had saved a baseline too.

    Thanks in advance.


    • 편집됨 jp-pm 2012년 5월 10일 목요일 오후 2:48 left out info
    •  

모든 응답

  • 2012년 5월 10일 목요일 오후 2:37
    중재자
     
     답변됨
    Insert Remaining Work Column and check if its 0 then add to it appropriate hrs. required to complete the task. This should fix the task.

    Sapna S

    • 답변으로 표시됨 jp-pm 2012년 5월 10일 목요일 오후 2:51
    •  
  • 2012년 5월 10일 목요일 오후 2:51
     
     

    Sapna,

    Perfect!

    Thank you for the answer.  Wow, :-)

    Thank you again....

    :-)

  • 2012년 5월 10일 목요일 오후 4:51
    중재자
     
     
    You are most Welcome jp-pm, seen you after a long time on the Forum :)

    Sapna S

  • 2012년 5월 10일 목요일 오후 8:26
     
     

    :-)

    Hi Sapna,

    Yes, I've been extremely busy PMing....

    :-)  Hopefully you don't see me this often (it would mean I'm confused) but thank you for acknowledging that

    I haven't been here for awhile....hehehehe.

  • 2012년 5월 11일 금요일 오전 5:28
    중재자
     
     
    Good to hear from you. You are most Welcome for the feedback.

    Sapna S