Duration x Res units = Work ?
-
vrijdag 10 september 2010 9:34
Hi,
In the previous versions of Project Professional, while assigning resources on tasks, we were using the logical equation :
Duration x Resource units = Work
In 2010 version, this equation doesn't work anymore. Do you know what the new logic is for that? Is there any document explaining that?
Thanks
Alle reacties
-
vrijdag 10 september 2010 9:45Moderator
Hi,
the calculation is still the same. But what is displayed in assignment units has been changed. For more information you can have a look at http://blogs.msdn.com/b/project/archive/2010/04/29/assignment-units-in-project-2010.aspx.
Regards
Barbara- Als antwoord gemarkeerd door WLID1966 vrijdag 10 september 2010 12:54
-
vrijdag 10 september 2010 12:54
Thanks Barbara,
I'll study that...