    Hi All

    I am very new to plug-In development for MS Project. Please guide me regarding this.My requirement is to show a pop-up at the time of project manager entering the resources. Is it possible? If yes, then guide me ....

    Thanks in Advance

    Regrds

    Ramesh Naidu

Alle reacties

  • dinsdag 22 juni 2010 15:34
     
     Antwoord

    Hello Ramesh,

    Yes you can do that.  It's easier if you are using Project Professional 2010.  Take a look at the Project 2010 SDK.  If you have future questions, you should post them in the Project Developers forum.

    Cheers!

    Michael Wharton, MBA, PMP, MCT


    Sincerely, Michael Wharton, MBA, PMP, MCT, MCSD, MCSE+I, MCDBA www.WhartonComputer.com
  • woensdag 23 juni 2010 14:45
     
     

    Hi Michael Wharton

    My requierement is to develop a plug-in for MS project. Which will allo project manager to enter resource email id at the time of Resource name Entering event. If project manager Enter resource name and then he press any of the button, automatically a pop-up will blow up asks manager to enter resource email Id. Then it will automatically send email t that resouce Name on task dead lines.

    Is it possible by using 2010 SDk?

    If yes, then i will completely moved to 2010 SDk..

    Please guide me regarding this ...

    Thanks In Advance.

    Regards

    Ramesh

  • woensdag 23 juni 2010 14:52
     
     

    Hello Ramesh,

    Take a look at the Project 2010 SDK.  The SDK provides source code, samples, help files and resource to get you started with building a custom solution.  Another place to look is CodePlex.com.

    For indepth question about project development and customization use the forum  http://social.technet.microsoft.com/Forums/en-US/project2010custprog/threads

     

    Cheers

    Michael Wharton, MBA, PMP, MCT


    Sincerely, Michael Wharton, MBA, PMP, MCT, MCSD, MCSE+I, MCDBA www.WhartonComputer.com
  • woensdag 23 juni 2010 17:23
    Moderator
     
     

    Hi,

    This is possible in any version of Project Professional and Standard that I know (2000, 2002, 2003, 2007, 2010)

    Greetings,

  • donderdag 24 juni 2010 8:01
     
     

    Hi Jan

    Is it possible really?

    If possible please provide me a proper guidence..

    Thanks In Advance

    Regards

    Ramesh

  • donderdag 24 juni 2010 13:39
    Moderator
     
     

    Hi,

    First you have to prepare the VBA nenvironment for using resource events; this can be found on pages 190 and 191 of the only book specializing on Project VBA:

    VBA Programming for Microsoft Office Project, by fellow MVP Rod Gill.

    Once you're there you can code whatever you want in the Projectbeforeresorucenew event.

    Greetings,