Timesheet ribbon calculating days incorrectly
-
maandag 23 april 2012 14:36
The timesheet status bar is calculating 1 day as 0.94.
The actual timesheet captures 1 day correctly. The default reporting units in Project Server is days and the number of hours in a standard timesheet day is 7.5. I'm not sure where else I need to check. Is this a known issue?
Alle reacties
-
woensdag 25 april 2012 14:33
Hi Leah,
Do all users and projects use a standard calendar? another thing to check within the project in MSP what is the standard day and week in hours?
Will
-
donderdag 3 mei 2012 14:01
Hi Will
We have two calendars, the project server standard calendar which we have changed to 7.5 hoursand a company specfic calendar which has 7.5 hours as standard. All our plans in MSP use the company specific calendar. Do you have any other ideas
Thanks for your help.
Leah
- Bewerkt door Leah M donderdag 3 mei 2012 14:01