    When I add a new custom field (duration) it shows "0 days" for all the task by default. Is it possible to change default "0 days" to none or blank.

    note: I do not want to change the lookup table values.

     

    HP

Alle reacties

  • donderdag 19 april 2012 7:50
     
     Antwoord

    Hi Harsh

    If the custom field is of duration type, then you can not change default "0 days" to blank or none.

    But yes you can use different type of custom field (If you have a Lookup Table).

    Thanks


    Manish

  • donderdag 19 april 2012 9:25
     
     

    If i may add to Manish answer, you can use a Text Custom field with lookup table and then you can set blanks and values of 1 days, 2 days Etc., but duration fields designed to have number of days/hours values...

    The problem with text field is you cannot use calculation like with duration field.

    This is why you can't use blank on duration field, you can't calculate numbers and text together (blank is like letters)


    Ofir Marco , MCTS P.Z. Projects