Timesheet is not active. Why?
-
woensdag 25 april 2012 5:44
I appoint task for resource and see this figure. Administrative time is active, but task time not active (grey). I can't fill values. Why?
Single Entry Mode is on. If i turn off SEM then this fields is active(white), but task status doesn't update.- Bewerkt door ultramaxim woensdag 25 april 2012 6:01
Alle reacties
-
woensdag 25 april 2012 6:59Can you just check if the task is locked for updates in Project Plan.
Abhijeet M. Mohite
-
woensdag 25 april 2012 7:07
Hi there,
you can only enter timephased data into tasks if
- your tasks are set to automatically scheduled
- your tracking method is set to time per period (specify hours).
You can change this behaviour within Project Professional:
- Change to auto-scheduled can be done on task level in field (column) task mode.
- Change to "Specify hours" at File - Info in the very right pane. If you are not allowed to change it here, you need to modify your server settings.
Default behaviour on server level:
- Tracking method: Project Web App - Server Settings - Tasks Settings and Display: Hours of Work done per period (you can choose if you want to force your PMs to use this method)
- Task Mode: Project Web App - Server Settings - Addtional Server Settings - Task Mode Settings. Defualt is here Manually Scheduled, change it to Automatically Scheduled.
Hope that helps.
Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82
- Als antwoord gemarkeerd door ultramaxim woensdag 25 april 2012 7:09
-
woensdag 25 april 2012 7:14
Thank you!!!
My tasks were set to manually scheduled. And that is why i had a problem!
-
woensdag 25 april 2012 7:17
You are welcome :)
I am glad that i was able to help.
Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82
-
woensdag 25 april 2012 12:13Just an FYI, The limitation of Time-phased work for manually scheduled tasks has been fixed in Service Pack 1.
Prasanna Adavi, PMP, MCTS http://thinkepm.blogspot.com
-
woensdag 25 april 2012 12:21thanks, i will try to install update.