Answered Timesheet is not active. Why?

  • woensdag 25 april 2012 5:44
     
     

    I appoint task for resource and see this figure. Administrative time is active, but task time not active (grey). I can't fill values. Why?

    Single Entry Mode is on. If i turn off SEM then this fields is active(white), but task status doesn't update. 
    • Bewerkt door ultramaxim woensdag 25 april 2012 6:01
    •  

Alle reacties

  • woensdag 25 april 2012 6:59
     
     
    Can you just check if the task is locked for updates in Project Plan.

    Abhijeet M. Mohite

  • woensdag 25 april 2012 7:07
     
     Antwoord

    Hi there,

    you can only enter timephased data into tasks if

    • your tasks are set to automatically scheduled
    • your tracking method is set to time per period (specify hours).

    You can change this behaviour within Project Professional:

    • Change to auto-scheduled can be done on task level in field (column) task mode.
    • Change to "Specify hours" at File - Info in the very right pane. If you are not allowed to change it here, you need to modify your server settings.

    Default behaviour on server level:

    • Tracking method: Project Web App - Server Settings - Tasks Settings and Display: Hours of Work done per period (you can choose if you want to force your PMs to use this method)
    • Task Mode: Project Web App - Server Settings - Addtional Server Settings - Task Mode Settings. Defualt is here Manually Scheduled, change it to Automatically Scheduled.

    Hope that helps.


    Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82

    • Als antwoord gemarkeerd door ultramaxim woensdag 25 april 2012 7:09
    •  
  • woensdag 25 april 2012 7:14
     
     

    Thank you!!! 

    My tasks were set to manually scheduled. And that is why i had a problem!

  • woensdag 25 april 2012 7:17
     
     

    You are welcome :)

    I am glad that i was able to help.


    Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82

  • woensdag 25 april 2012 12:13
     
     
    Just an FYI, The limitation of Time-phased work  for manually scheduled tasks has been fixed in Service Pack 1.

    Prasanna Adavi, PMP, MCTS http://thinkepm.blogspot.com

  • woensdag 25 april 2012 12:21
     
     
    thanks, i will try to install update.