Project web App modified icon is not coming in the sample/ Templates Reports in prject server 2010

Unanswered Project web App modified icon is not coming in the sample/ Templates Reports in prject server 2010

Wszystkie odpowiedzi

  • 14 maja 2012 10:42
     
     

    Hi Lovely,

    You have changed the site icon of PWA. but this  icon is from the root site:
    http://servername/_layouts/images/titlegraphic.gif

    Try to change the titlegraphic.gif from the BI center> Site settings> Title Description & Icon.
    http:// servername/PWA/ProjectBICenter/_layouts/prjsetng.aspx


    Please replace the servername from the url with the servername you are using in your PWA instance.

    Hope this helps.


    If you found this post helpful, please "Vote as Helpful". If it answered your question, Plase "Mark as Answer".
    Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82


  • 14 maja 2012 11:19
     
     

    Hi Amit,

    I have changed it for BI site already. I am site the Icon in the BI , also Icon is avaqilable in the Sample Reports Library Page. The Icon is missing when we are opening a report item from the library.


    Thanks, Lovely


    • Zmodyfikowany przez Rose 25 14 maja 2012 11:20
    •  
  • 14 maja 2012 11:46
     
     

    Hi Lovely--

    By any chance, are you using the mutilple web servers. If yes,  in that case, the icon image needs to be copied to the same folder in each web servers. Try deleting the IE temporary files/cache & test it.


    If you found this post helpful, please "Vote as Helpful";. If it answered your question, Plase "Mark as Answer" . Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82