An Unknown Error Has Occurred - Project Server 2010 - Tasks Page
-
6 lipca 2012 18:53
Greetings! Some of my resources are recieving the error "An Unknown Error has occurred" (in red) when trying to access their TASKS Page in Project Server 2010.
I've researched this error quite a bit and am finding suggestions and answers pretty much all over the board. Before I have my server people start installing a slew of hot fixes - I want to know if anyone has an idea of the underlying cause for this error. Since this issue doesn't affect everyone (i.e. I can access my task page), is it possibly related to the actual schedule in which they have assignments?
Any help is appreciated.
Thanks!
~Randy
Wszystkie odpowiedzi
-
6 lipca 2012 20:17
-
7 lipca 2012 09:13
Hi Randy,
As Hrishi said, I would check the ULS logs for the underlying cause. It could be data related, database performance related etc.
Have you set up the Project Server databae maintenance plans? http://technet.microsoft.com/en-us/library/cc973097.aspx
I have seen this issue before, in my case it was related to the database indexes / statistics not being updated and you could see a SQL timeout in the ULS logs. Might be worth running the following SQL against the Project Server PWA databases and retesting:
EXEC SP_updatestats
Thanks
Paul
Paul Mather | Twitter | http://pwmather.wordpress.com
-
7 lipca 2012 19:03
Hi Randy,
this article is probably about same issue http://social.technet.microsoft.com/Forums/en-US/projectserver2010general/thread/71c3afa0-f1a1-4768-9ba5-ebcd712f4f02
I had same problem but with only one resource.
Tomas
- Oznaczony jako odpowiedź przez Randy W. Knight 11 lipca 2012 14:16