DPM 2007 Detail Inventory Job

Traitée DPM 2007 Detail Inventory Job

  • 16 lutego 2012 04:07
     
     

    HI, i am using DPM 2007 with Ultrium 3 library. detault inventory job runs at time of the backup running. any way to change the inventory job schedule, found job in SQL, changed the job times but didn't help.

    please suggest how to change the default inventory job timing.

    Mukul...

Wszystkie odpowiedzi

  • 16 lutego 2012 06:41
     
     Odpowiedz

    i am able to solve this with the power shell..

      Set-MaintenanceJobStartTime [[-StartTime] <DateTime>] -DPMServerName <Strin
        g> -MaintenanceJob <HouseKeepingJobs> [<CommonParameters>]

    • Oznaczony jako odpowiedź przez Mukul Sharma1 16 lutego 2012 06:41
    •