There is not enough memory to complete this operation when trying to close the Project Professional

Answered There is not enough memory to complete this operation when trying to close the Project Professional

  • terça-feira, 28 de fevereiro de 2012 01:16
     
     

    When trying to close the project file (Project Professional 2010) instance some users receive the error(see figure) complaining about insufficient memory. But looking at the Windows Task Manager (same screen shot),  we do not see any performance issue.

    We are on Sp1 with Dec 2011 CU. The box accessing the project professional has 3 GB so no memory issue. No sure what is causing this error.





    RRS


    • Editado srituraj terça-feira, 28 de fevereiro de 2012 01:17 invalid text
    •  

Todas as Respostas

  • terça-feira, 28 de fevereiro de 2012 02:34
    Moderador
     
     

    Obviously that shouldn't happen. No idea what's causing it, so is this a file created by Project 2010 or 2007? If 2007 or earlier, it's best to have that version updated to latest SP before opening in 2010.

    If this isn't the problem, what memory do PCs not having this problem have?

    Is the file on a network? If so, might there be network problems?

    Rod Gill

    The one and only Project VBA Book Rod Gill Project Management

  • terça-feira, 28 de fevereiro de 2012 20:26
     
     

    Hi Rod,

    This is a file created in Project Professional 2010 and both server and client are patched upto December 2011 CU patch. Some of them have as low as 2 gigs on Windows XP.

    Thanks


    RRS

  • quarta-feira, 29 de fevereiro de 2012 21:23
     
     Respondido

    Hi srituraj,

    Try to set you cache a bit higher...By default it is set to 50 MB; I set it  to at least 1000MB. (File/Options/Save/Cache size limit...)

    BTW: are you working with a 32 or a 64-bit MSP?

    Regards
    Wim

    • Sugerido como Resposta Project User quinta-feira, 8 de março de 2012 11:06
    • Marcado como Resposta Mike GlenModerator sexta-feira, 27 de abril de 2012 21:03
    •  
  • sexta-feira, 2 de março de 2012 10:10
     
     

    Hi srituraj,

    The problem is likely to be in cache size as Wim says. Also I faced such kind of error messages trying to enter invalid data into resource calendar, e.g. work week name that exceeds 127 symbols.

    Hope this will help.

    Regards,
    Alexander

  • segunda-feira, 5 de março de 2012 22:03
     
     

    Hi Win,

    It is a 32 bit MSP. I will try this option.

    Thanks

    Ritu


    RRS

  • quarta-feira, 7 de março de 2012 22:03
     
     

    Hi Ritu,

    Can you mark the thread as answered? otherwise it remains open...

    Regards
    WIm