Acceleration
-
segunda-feira, 21 de maio de 2012 20:17How can I change working times of just a single task without affecting all the other tasks that fall on the same day?
Todas as Respostas
-
segunda-feira, 21 de maio de 2012 21:04Moderador
Hello,
If you have a resource assigned, you may alter the resource's calendar and project will schedule the task based upon the resource's calendar. If you don't have a resource assigned, you may create a new calendar (copy the existing project calendar), modify the working time for the single day and then assign the new calendar as a task calendar.
I hope this helps.
Julie
- Marcado como Resposta Mike GlenModerator terça-feira, 17 de julho de 2012 20:19
-
terça-feira, 22 de maio de 2012 07:36Moderador
Create a task calendar, if only that task need to be changed for Working Time, refer to link below for creating the Calendar.
http://office.microsoft.com/en-us/project-help/create-a-calendar-for-a-task-within-project-HA010377765.aspx
Sapna S
- Marcado como Resposta Mike GlenModerator terça-feira, 17 de julho de 2012 20:19