Can the Status Report feature in Project server 2010 be modified
-
terça-feira, 14 de setembro de 2010 13:02The client I'm working with have a status report format that they use and would like to maintain this format, is there a way the status report feature in Project server can be modified to have tables and/or indicators
Todas as Respostas
-
terça-feira, 14 de setembro de 2010 13:03Moderador
-
terça-feira, 14 de setembro de 2010 14:39what would you suggest as the best concept and how do you suggest i carry it out?
-
terça-feira, 14 de setembro de 2010 16:05Moderador
I've seen a SharePoint List used to collect updates (which can even be donevia incoming e-mail). Then on a weekly basis aggregate that list into astatus report in InfoPath or SSRS. In another section on the same report,you can pull critical task data, and you're there.- Andrew Lavinsky- Sugerido como Resposta Christophe FiessingerMicrosoft Employee, Owner terça-feira, 14 de setembro de 2010 17:32
- Marcado como Resposta Marc Soester [MVP]MVP, Moderator quinta-feira, 16 de setembro de 2010 04:23