can we filter out the fourth level tasks based on the level 1 and Level 2 tasks in project server 2010?

Răspuns can we filter out the fourth level tasks based on the level 1 and Level 2 tasks in project server 2010?

  • 4 mai 2012 14:00
     
     

    Hi
    I have four levels of Task in the project Plan.I have to create report on fourth level task and need to do the the filtering of these tasks by selecting task Level 1 and Level2

    that is I need to select a value for Level2 Task, then fourth level subtasks of this selected level 2 task only be available in the report.

    Please help


    Thanks, Lovely

Toate mesajele

  • 4 mai 2012 14:17
     
     Răspuns
    Hi there-- Hope the below thread helps. http://social.technet.microsoft.com/Forums/en-US/projectserver2010general/thread/2035bc16-0f64-415c-8451-980821f14b02 Thanks,

    Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82

  • 7 mai 2012 14:41
     
     

    Thanks a lot Amit.

    The thread you have mentioned really helped and it worked for me :)


    Thanks, Lovely