Block issue date column baseline after saving the baseline.

Întrebare Block issue date column baseline after saving the baseline.

  • 27 aprilie 2012 11:33
     
     

    Hi Friends,

    You can block the publication in edition dates of the column baseline in MS Project 2010 through the event ProjectBeforeTaskChange.

    Returning to the state if possible example how to mount this macro in VBA.

    Thank you.


    Hezequias Vasconcelos