Answered How to add new PDP in EPT

  • 3 mai 2010 07:26
     
     

    Hai..

    I want to add new New page/PDP in EPT.

    How to add new custom PDP in EPT.

     

    Thanks in advance

    iqbalkmk

     

Toate mesajele

  • 3 mai 2010 10:54
    Moderator
     
     

    Hi,

    Assuming you have already created the new PDP, to add it to an EPT, you need to go to Server Settings > Enterprise Project Types  and assign the PDP to the EPT. If you are using a workflow, make sure you update the relevant stage so that the PDP is visible at the correct stage for your workflow.

    Regards,

     

    Alex.


    Alex Burton www.epmsource.com
  • 3 mai 2010 14:48
    Proprietar
     
     
    Creat new PDP first, then create the EPT and use that newly created PDP or edit EPT afterward with proper PDP.
    http://blogs.msdn.com/chrisfie
  • 4 mai 2010 06:45
     
     

    Hai Chris,

    Thank you for giving advise.

    But i didnt find PDP (which i created) in new Page/PDP drop down list in EPT page.

     

    I want to add my PDP in to the New page/Project Detail Page in EPT. There are only PDP in that Drop down list which are Project details and Project information only.

    How can i add..

    Thanks in advance

    iqbalkmk

  • 4 mai 2010 07:32
    Moderator
     
     Răspuns

    Hi,

    When you create a PDP it has a Page Type associated with it that determines where the PDP shows up in the configuration GUI. To make your PDP show up in the New Project Page drop down list, make sure you have the Page type set to (2) New Project.

    Regards,

    Alex.


    Alex Burton www.epmsource.com
    • Marcat ca răspuns de iqbalkmk 4 mai 2010 13:00
    •  
  • 11 mai 2010 07:47
     
     

    Hai Alex

    Thank You very much....