Deleting Projects in PWA 2010
-
26 iulie 2010 21:35
Use to be when you deleted a project in 2007 it showed in the Archive db.
I have tested 3 different instances of 2010 and nothing shows in the Archive db after a project deletion.
Is this new or a bug as it will cause issues if someone is thinking it will be there after deletion from Published db.
yubouybouy
Toate mesajele
-
27 iulie 2010 04:03Proprietar
out of the box if a project is deleted it's gone for good unless you have scheduled a backup similar to 2007
Blog | Facebook | Twitter | Posting is provided "AS IS" with no warranties, and confers no rights.
Project Server TechCenter | Project Developer Center | Project Server Help | Project Product Page- Propus ca răspuns de Alexander Burton [MVP]MVP, Moderator 27 iulie 2010 11:50
- Marcat ca răspuns de Christophe FiessingerMicrosoft Employee, Owner 28 iulie 2010 23:30
-
28 iulie 2010 23:29Moderator
Hi
You will need to setup the backup. Once you have set up the backup a project will be backed up into the archive database when:
- the backup is running ( e.g. nightly) AND
- a project has been amended since the last backup
You can settup your backup by naviagting to Server Settings > Daily Schedule Backup.Hope this helps
Marc Soester [MVP] http://marcsoester.blogspot.com- Propus ca răspuns de Marc Soester [MVP]MVP, Moderator 29 iulie 2010 06:44