[EPM 2010] Define the focus on a specific task.

Unanswered [EPM 2010] Define the focus on a specific task.

  • 10 mai 2012 09:42
     
     

    Hello,

    I was wondering if it would be possible to define a specific rule when you open your projet detailed view.

    Example: I have found in the server setting, that you can manage the format view per view (Task Summary, Task Detail ...)

    So, i have mentioned that i would like to see the entire tasks collapsed.

    Now my question: Is it possible to collapse every tasks except one (based on a specific rule like) ?

    Thank you,


    Math

Toate mesajele

  • 10 mai 2012 09:54
     
     

    Hi Math,

    When you create a View formatting in Manage views of PWA Server settings. There is no out of box option to show a specifc task (collapse every tasks except one ) but on another note if you have the specific task is standard on each project & lets say on Outline level 2. You may setup the view to show the Outline level 2 in view formatting.

    You may create a custom PDP page with JSgrid or standard grids which can show the data as desired.


    Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82