Timesheet ribbon calculating days incorrectly

Întrebare Timesheet ribbon calculating days incorrectly

  • 23 aprilie 2012 14:36
     
     

    The timesheet status bar is calculating 1 day as 0.94. 

    The actual timesheet captures 1 day correctly.  The default reporting units in Project Server is days and the number of hours in a standard timesheet day is 7.5.  I'm not sure where else I need to check.  Is this a known issue?

Toate mesajele

  • 25 aprilie 2012 14:33
     
     

    Hi Leah,

    Do all users and projects use a standard calendar? another thing to check within the project in MSP what is the standard day and week in hours?

    Will

  • 3 mai 2012 14:01
     
     

    Hi Will

    We have two calendars, the project server standard calendar which we have changed to 7.5 hoursand a company specfic calendar which has 7.5 hours as standard.  All our plans in MSP use the company specific calendar.  Do you have any other ideas

    Thanks for your help.

    Leah


    • Editat de Leah M 3 mai 2012 14:01
    •