I am trying to create ~100 "as-built"schedules to MSP Server 2010 (on SP 2010). I would like to create them in Pro, then import an XLS with actual (Generic) Resource Name, Work (hours), Actual Start/Finish, etc. The problem is after I create
a shell in Pro and upload it to the server, subsequent changes based on my Excel Template don't stick. I can see the imports in Pro, then Save/Publish/Check-In to the server, but I don't see the updates in PWA. What's strange though is then I download
the project from the server and the imported data is still there. I have checked Server Settings that would seem relevant; such as,
Timesheet Setting and Defaults and everything seems to be fine. I feel like there is some button I need to push to propagate the (non-timesheet) data out there. I am the admin and have rights
to everything. What am I missing?