Hello,
Had a quick question .. has anyone created/used a setup/batch file that can be emailed/shared among end users, which will automatically add the project server account to Microsoft Project Pro 2010.
Rather than going to each desktop and entering the information (which is time consuming if you are dealing with a big installation), or asking the end user to enter the details (which is prone to errors). I would rather have them run a file which will configure Project pro for them.
Thanks.
Toate mesajele
-
6 iulie 2012 05:25
Hi
the account is stored in the registry, Current User hive.
You can export a .reg file from there and import that by doubleclick.
HKEY_CURRENT_USER\Software\Microsoft\Office\14.0\MS Project\Profiles
Regards
Christoph
- Marcat ca răspuns de Brian Smith - MSFTMicrosoft Employee, Moderator 9 iulie 2012 15:52
-
9 iulie 2012 16:32Thanks