Regarding Task publishing through PWA.
-
2 mai 2012 23:01
I have one question regarding Task publishing through PWA.
if i publish the submitted hours from my team through PWA (Approve Center -> History), are the SPI and CPI automatically updated in the SSRS reports? or I need to manually publish my Work Plan again?
We are using MSP 2010...
I believe publishing through PWA also update the values to reports, but do SPI and CPI are also updated?
thanks in advance.
BR
Irshad
...irshad
Toate mesajele
-
2 mai 2012 23:41
Hello Irshad,SPI and CPI values are calculated by scheduling engine used by Project Professional. PWA scheduling engine and Project Pro scheduling engine both are not identical
When you publish a project plan via PWA, we call it as partial publishing and full publish when Project Professional is used.
Hence you need to perform full publish to calculate these values.
http://office.microsoft.com/en-us/project-help/spi-fields-HP001025917.aspx
Hrishi Deshpande – DeltaBahn Senior Consultant
Blog | < | LinkedIn- Propus ca răspuns de Hrishi.Deshpande 4 mai 2012 15:25
-
3 mai 2012 17:19Thanks Hrishi !