25 พฤษภาคม 2553 19:16
Several of us have noticed that when we select Project->Reports->Assignments->Who Does What a "Project Summary" report comes up instead of the "Who Does What"
I tried to copy a new Who Does What from GLOBAL.MPT in, naming it "Who Does What 2" and selecting that report renders as a Task sheet.
How do we restore to default reports?
Did we corrupt our .MPP file somehow?
ตอบทั้งหมด
-
25 พฤษภาคม 2553 20:51ผู้ดูแลHi Glenn,Welcome to this Microsoft Project newsgroup :)I can't reproduce this in Project Standard. Are you using Project Pro? Does this happen with other projects or other PCs?FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htmHope this helps - please let us know how you get on :)
"Glenn Scott" wrote in message news:0aa28209-a78f-4e35-ade1-c81fd30ba26d...Several of us have noticed that when we select Project->Reports->Assignments->Who Does What a "Project Summary" report comes up instead of the "Who Does What"
I tried to copy a new Who Does What from GLOBAL.MPT in, naming it "Who Does What 2" and selecting that report renders as a Task sheet.
How do we restore to default reports?
Did we corrupt our .MPP file somehow?
- ทำเครื่องหมายเป็นคำตอบโดย Christophe FiessingerMicrosoft, Owner 25 พฤษภาคม 2553 23:45
- ยกเลิกการทำเครื่องหมายเป็นคำตอบโดย Glenn Scott 1 มิถุนายน 2553 15:42
-
26 พฤษภาคม 2553 8:17ผู้ดูแล
Hi Glenn,It does sound like a corrupt global.mpt. I've seen this sort of issue before when reports have been copied over to the Enterprise Global Template - are you using Project Server? If so, clear your local project cache (cd %appdata%/microsoft/ms project/14 and delete the cache folder). If you are not using Server, I would remove Project (making sure the global.mpt is removed) and then re-install it.One other thing - do you all see this issue on the same project, or are they on different projects?"Glenn Scott" wrote in message news:0aa28209-a78f-4e35-ade1-c81fd30ba26d...Several of us have noticed that when we select Project->Reports->Assignments->Who Does What a "Project Summary" report comes up instead of the "Who Does What"
I tried to copy a new Who Does What from GLOBAL.MPT in, naming it "Who Does What 2" and selecting that report renders as a Task sheet.
How do we restore to default reports?
Did we corrupt our .MPP file somehow?
Ben Howard [MVP] http://appleparkltd.spaces.live.com/- ทำเครื่องหมายเป็นคำตอบโดย Glenn Scott 1 มิถุนายน 2553 15:48
-
1 มิถุนายน 2553 15:46
Ben -- user sees the report "corruption" on *all* projects.
This user has not used Project Server.
Good plan to re-install Project Pro 2010. Should have thought of it -- will try that. But Proj should be more robust than that.
-
1 มิถุนายน 2553 22:44ผู้ดูแลApologies, I tend to assume (incorrectly in this case) that anyone using project professional is connecting to a project server. This issue could be seen with a corrupt Global Template - this shows in all projects as the reports by default are stored in the global template.
Ben Howard [MVP] http://appleparkltd.spaces.live.com/