Con risposta Status date in Timeline View

ตอบทั้งหมด

  • 15 มกราคม 2553 16:06
    ผู้ดูแล
     
     คำตอบ
    Hi Winson,

    Welcome to this Microsoft Project newsgroup :) As far as I know, there's no built-in way to do this. However, you could create a milestone (called it Status Date?)and show it on the Timeline. Double click on it and enter the Status Date you want. As Status Date defaults to 1700, I suggest you show the times as well on the timeline so you can synchronise the times.

    FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm

    Hope this helps - please let us know how you get on :)

    Mike Glen
    MS Project MVP
    See http://tinyurl.com/2xbhc for my free Project Tutorials
    • ทำเครื่องหมายเป็นคำตอบโดย Winson, PMP,PMI-SP,MCTS 17 มกราคม 2553 12:35
    •