Răspuns column "summary" filter!!

  • 18 มกราคม 2553 8:52
     
     

    1. display autofilter
    2. insert ""summary" column
    3. select "summary"="No" (It doesn't work and all tasks remain on screen including summary and non-summary tasks)

    ps. it is the same when applying a customed filter "Summary equals No".

    I don't think it is normal.
    Anyway, how could I filter out only tasks without any child tasks??

ตอบทั้งหมด

  • 18 มกราคม 2553 10:10
    ผู้ดูแล
     
     คำตอบ

    Hi Winson,

    default option for filters is "Show related summary rows". You can verify that if you click on your filter symbol on the summary column -> Filters -> Custom …. -> Save …. There you can see that "Show related summary rows" is activated.
    If you create a custom filter you can deactivate this option.

     

    • ทำเครื่องหมายเป็นคำตอบโดย Winson, PMP,PMI-SP,MCTS 18 มกราคม 2553 11:21
    •