Answered Dates on the Timeline Feature

  • 21 ธันวาคม 2552 17:21
     
     

    Hi,

    Can we get the new timeline feature to display Baseline dates rather than schedule dates or both?

    Thank-you and Best Regards,

    Carmelo Lattuca

ตอบทั้งหมด

  • 21 ธันวาคม 2552 20:54
    ผู้ดูแล
     
     คำตอบ

    Hi Carmello,

    Welcome to this Microsoft Project forum :)

    The new timeline feature has taken over the feature of rolling up tasks to summay in earlier versions.  There is no way to include baselines, sorry :(

    FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm

    Hope this helps - please let us know how you get on :)

    Mike Glen
    MS Project MVP
    See http://tinyurl.com/2xbhc for my free Project Tutorials