Beantwortet Resource Availability

  • 1 พฤษภาคม 2555 20:12
     
     
    Using Project 2007 Standard.  I would like to know if there is a way to set resource availability to a certain work period only.  The setting in the Resource Sheet only allows you to set unit% for set periods.  I would like to set a period of time where a resource is only available and cannot work beyond.  We have contractors that budget will only allow us to have for 11 weeks.  I want to be able to fill their time but alert me when they have reached their contract end date.  Using exceptions does not do what I want.  Using a resource pool if that makes a difference.  Recommendations?

ตอบทั้งหมด

  • 1 พฤษภาคม 2555 21:08
    ผู้ดูแล
     
     คำตอบที่เสนอ

    Simplest solution is to add a deadline to the contractor's last task with the 11 week deadline. If the finish date passes that date a red diamond will appear in the indicator column.

    There are various other solutions, but their use depends on how your schedule is structured and what's most important for your schedule to communicate to your stakeholders.


    Rod Gill

    The one and only Project VBA Book

    Rod Gill Project Management

    • เสนอเป็นคำตอบโดย Project User 1 พฤษภาคม 2555 22:43
    •  
  • 2 พฤษภาคม 2555 14:31
     
     
    Thanks Rod.  I appreciate your response.  Your suggestion helps somewhat but doesn't solve all my problems.  Is there a solution that attaches the deadline to the resource's availability instead of their last task?  There work periods are hard stops.  We are trying to balance the workload amongst the contractors and I am adding/juggling tasks between them.  I would like to have a way that does not allow me to over-allocate them.  Thanks again.
  • 2 พฤษภาคม 2555 15:25
    ผู้ดูแล
     
     

    Pardon me for bumping in.  There is an option of setting availability through the Resource Information dialog.  However, this will not prevent you from assigning resources past their availability date -- but will immediately flag them as overallocated.

    Julie

  • 2 พฤษภาคม 2555 20:39
    ผู้ดูแล
     
     คำตอบ
    Add a milestone that communicates end of contractor work and link it to end of contractor workstreams. Now that milestone will finish after all contractor work is finished. Add deadline to this milestone.

    Rod Gill

    The one and only Project VBA Book

    Rod Gill Project Management

    • ทำเครื่องหมายเป็นคำตอบโดย Joseph Das 7 พฤษภาคม 2555 13:33
    •  
  • 7 พฤษภาคม 2555 13:34
     
     
    Thanks Rod.  That workaround will do the trick.