Project Server 2010 - Notification on new task, but not on old task with new assignment.

Proposed Answer Project Server 2010 - Notification on new task, but not on old task with new assignment.

  • 25 กรกฎาคม 2554 17:15
     
     

    Hello everyone,

    in an installation of Project Server 2010 (SP1CU06/11), I have setup notifications for myself as follows:

    Checked "I receive a new task assignment in my projects", unchecked everything else.

    Now, when I create a new task, assign myself and publish, I get an email. When I create a task and assign myself like a team member would in PWA (Task or Timesheet page / assign myself to task), it get an email. But when I create a task in MS Project, publish it, and then still in MS Project assign myself and publish it again, I do not get an email.

    Does anyone else experience this behaviour? Has this been around before, or is this issue new in SP1 and/or CU6? Any feedback or comment would be appreciated.

    Kind regards,
    Adrian

ตอบทั้งหมด

  • 27 กรกฎาคม 2554 18:34
     
     
    If you published a task without assigning a resource, wouldn't you automatically be the assignment owner and therefore should have gotten an email triggered that time?  Did that happen?  (This is the behavior I see in 07)
    Terrie T - MCTS - PMP - MBA****PMO & Project Server Admin
  • 28 กรกฎาคม 2554 22:39
     
     

    When publishing a task with no resource, then there is no assignment and no assignment owner either.

    In my tests, I was the project manager/creator/owner as well as the resource since I assigned myself, and I never get a mail in this process. When I create a task, assign myself and publish, I always get a mail. If I create the task, publish, and assign myself later, I never do.

    I checked only the "I receive a new task assignment in my projects" checkbox, since I only want to be informed about new tasks. but not about any other changes.

    Thank you for having looked into it in 2007 though.

    Kind regards,
    Adrian

  • 18 มกราคม 2555 20:36
     
     คำตอบที่เสนอ

    What we found is that you need to check off both boxes:

    Task Alerts

    In certain cases Project Server thinks the task / assignment is modified even when the assignment itself is new. This can happen if your project has say 20 tasks listed, and then you go about assigning resources at a later point in time - such as your example.

    I found by setting on these both checkboxed the resource indeed gets a notification for new task assignment in all cases - but the drawback is they are also being notified when something changes (too much spam as well).


    Nilesh Kelkar | nkelkar.wordpress.com
    • เสนอเป็นคำตอบโดย Nilesh Kelkar 18 มกราคม 2555 20:37
    •  
  • 5 พฤษภาคม 2555 10:13
     
     
    In certain cases Project Server thinks the task / assignment is modified even when the assignment itself is new. This can happen if your project has say 20 tasks listed, and then you go about assigning resources at a later point in time - such as your example.

    Hi Nilesh,

    that does seem like a plausible explanation. So, the two check boxes actually function as:

    • I receive an assignment on a new task.
    • A task is changed, and I now have an assignment on this task.

    Did anyone get a more official confirmation on this issue?

    Kind regards,
    Adrian