Single entry mode after February CU
-
21 มีนาคม 2555 8:46
Hi
After aplying February 2012 CU on Project Server 2010 we have a problem with single entry mode.
If we enter hours on tasks then the entered hours are not shown in timesheet. Vice versa work OK. So if we enter work in timesheet the entered hours for this task are also shown in task view.
ตอบทั้งหมด
-
21 มีนาคม 2555 11:23
Hi
This is by design and it came with december 2011 CU.
http://social.technet.microsoft.com/Forums/en-US/projectserver2010general/thread/3815027a-a9d5-450c-80e9-a10733ddc16f
Here you can find Best practices for submitting and reporting on actual work
http://technet.microsoft.com/en-us/library/hh694531.aspxTomas
-
21 มีนาคม 2555 12:13
HI
This could not came with december 2011 CU, because we have this installed and it works without a problem. The problem begins after February 2012 CU.
Also in Best practices "http://technet.microsoft.com/en-us/library/hh694531.aspx" which are update Januar 24, they say "When both views are available, users can enter actual work in either view, and the data is persisted in both views"