HOW WILL USER ENTER VALUES IN MY TASK??
-
7 พฤษภาคม 2555 10:48
Hii
i have added certain custom fields in My task,such as Travel cost,Daily allow,accomodation charges,so that in addition to task progress user can also mention the various expenses he had spend while working on the task,but there is one issue,how will the user enter values in some custom fields like Daily Allowance,if the task duration is more than 1 day,becoz there is only one row for each task in my task,and fields like travel cost,daily allow are different for each day,so team member should enter them separetely,say for eg task 1 is of 5 day,on 1 day he had spent 500 on DA,200 ON tRAVEL COST,ON 2 DAY HE HAD SPEND 300 ON DA,200 ON TRAVEL COST ETC
ANY HELP WILL BE GREATLY APPRECIATED
THANKS
ตอบทั้งหมด
-
7 พฤษภาคม 2555 11:47ผู้ดูแลThere's no way out of the box to do that that I am aware of. You're probablytalking customization.At the end of the day, there are no custom timephased fields - although youcan repurpose a spare baseline field to that effect.
Andrew Lavinsky [MVP] Blog: http://azlav.umtblog.com Twitter: @alavinsky -
7 พฤษภาคม 2555 11:59
hi andrew
i have shifted those custom fields to My Timesheet View,here user has the option to insert task(from ribbon),i.e if user is assigned to task t1,he has the option in My timesheet to again insert a row of task t1 and enter values in it,BUT THERE IS ONE MAJOR PROBLEM WITH IT,WHEN I SEND THE INSERTED ROW WHICH I HAVE INSERTED MYSELF TO MY STATUS MANAGER FOR APPROVAL,IT IS NOT SHOWN TO STATUS MANAGER
DO YOU HAVE ANY IDEA WHY IT IS HAPPENNING
THANKS
-
7 พฤษภาคม 2555 12:39ผู้ดูแล
-
7 พฤษภาคม 2555 16:10i was only changing the custom field,,do you tjink that could be a reason??