MS Project 2010 - How to add Custom date formats
-
29 Nisan 2012 Pazar 06:48
Is there a way to add Custom Date formats in MS Project?
e.g. I need to display date as mmm-yyyy (Feb-2012). The available list does not include such a format.
Regards,
Manoj
Tüm Yanıtlar
-
29 Nisan 2012 Pazar 17:12
It is not possible to apply a customized date display format to Project in application level.
We can display date values of any field in another custom field using a formula. For example, the following formula in Text1 field displays Start dates in mmm-yyyy format: Format( [Start], "mmm-yyyy")
Regards.
- Yanıt Olarak Öneren Manish M Upadhyay 30 Nisan 2012 Pazartesi 08:46
- Yanıt Olarak İşaretleyen Julie SheetsMVP, Moderator 02 Mayıs 2012 Çarşamba 20:17
-
29 Nisan 2012 Pazar 21:20Moderatör
Technically date formats can be changed, but only by changing the date format under Windows' control panel and regional settings. Since you can't anticipate what other PC's settings will be, Project User's suggestion of using a custom Text field is the better option.Rod Gill
The one and only Project VBA Book
Rod Gill Project Management
- Yanıt Olarak Öneren Rod Gill MVPMVP, Moderator 29 Nisan 2012 Pazar 21:21
- Yanıt Olarak İşaretleyen Julie SheetsMVP, Moderator 02 Mayıs 2012 Çarşamba 20:17