    Good morning all,

    recently our resource pool has become corrupt. Due to the amount of unrequired historic information contained in the pool, it has been decided a new resource pool is required - i have the enviable task.

    Can i link these plans to an empty resource pool, and the resource pool will populate itself from the plans, or do i have to populate the resource pool first (this will be a lengthy process that i am keen to avoid..)?

全部回复

  • 2012年7月11日 11:32
    版主
     
     已答复

    Hi,

    YOu cxan indeed link the projects to an empty pool.

    Just a piece of advice: do give the new pool a DIFFERENT FILE NAME - I've known problems if you save it with the same name.

    Greetings,

    • 已标记为答案 rapscalli 2012年7月11日 15:30
    •