MS Project Server: Enterprise Custom Fields and Cubes

已答复 MS Project Server: Enterprise Custom Fields and Cubes

  • 2009年11月3日 12:55
     
     
    We have a few Project level and Task level Enterprise Custom Fields. The fields have been set to appear in Cubes(Cube configuration page). When a view is created from MSP_Project_Timesheet Cube, the custom fields appearing in the field list. When these columns are added to the view, the data (Actual Work) becomes blank. What could be causing this issue?

全部回复

  • 2009年11月3日 19:58
    版主
     
     已答复
    Hello VKShenoy,

    See my reply to your other message suggesting a re-post to the newsgroup for Project server at:
    http://www.microsoft.com/office/community/en-us/default.mspx?dg=microsoft.public.project.server&lang=en&cr=US

    Julie
    Project MVP