TIME SCALE OUTLAY.
-
2010年3月3日 15:11
Hello, is there a way that i could get microsoft projects to define tasks based on the start and end time, rather than dates, and duration .
to further :
If i have the following columns
Task Name
Duration
Start
Finish
Microsoft project will place the project attributes based on the start and finish which is in days.
I either a: Need to get the start and finish to a time or times plus days , b: i need to get the start and finish to be start time and finish time.
Also is there any other column i could create that would make scale look at the start and finish times, as time is ket to my project task no days.
全部回复
-
2010年3月3日 20:20版主
Hi IKEGNE,
1. You can enter time of day everywhere in Project as 3/3/10 11:33
2. Project willl also SHOW time of day in all date columns (talking Project 2010, the subject of this newsgroup) through
File, Options, general, Select in Date Format teh one with the time of day included
3. Have you tried entering start, then finish? It will do as you request.
(Note that this is not considered best practice but you may have special tasks)
Hope this helps,
Jan De Messemaeker- 已建议为答案 Jan De Messemaeker - Project MVPMVP, Moderator 2010年3月4日 10:01