IT 专业人士的资源 > 论坛主页 > Windows HPC Server Developers - General > Overhead with using CCS scheduler using MPI
提出问题提出问题
 

已答复Overhead with using CCS scheduler using MPI

  • 2008年12月8日 23:37jingsongw 用户奖牌用户奖牌用户奖牌用户奖牌用户奖牌
     
    I'm setting up a compute cluster that uses MPI to generate calculations on the fly in short amounts of time <3s. I was wondering what kind of overhead times I would possibly see if I submitted jobs using the CCP API, or should I just use the Cluster.ExecuteCommand method instead?

    If neither of these is a possibility because the overhead of the CCP framework is too large, is there a way to bypass that and still harness the power of the MPI.NET?

答案

  • 2009年6月25日 1:56Don PatteeMSFT, 版主用户奖牌用户奖牌用户奖牌用户奖牌用户奖牌
     已答复
    You may want to look at the 'parametric sweep' and 'SOA'/'WCF' features in the HPC documentation. Those both enable more calculations to be done without paying a full job submission penalty for each one.

全部回复

  • 2009年6月25日 1:56Don PatteeMSFT, 版主用户奖牌用户奖牌用户奖牌用户奖牌用户奖牌
     已答复
    You may want to look at the 'parametric sweep' and 'SOA'/'WCF' features in the HPC documentation. Those both enable more calculations to be done without paying a full job submission penalty for each one.