PSI Delete Forecast Start/Finish or Actual Start/Finish

Unanswered PSI Delete Forecast Start/Finish or Actual Start/Finish

  • 2012年5月30日 21:06
     
     
    Hi I am running a strange issue with Project Server PSI.  I have tried to set the Forecast Start/Finish date to null when there are no actual or set the Actual Start/Finish date to null, the Project Server doesn't take effective to the request.  Is there a way to empty the Forecast Start/Finish and Actual Start/Finish use the Project Server PSI?  Please help.  Thanks in advance.

所有回覆

  • 2012年5月31日 4:18
    版主
     
     

    You might want to check the actual value that's in there.  As I recall 'NA' <> Null. 


    Andrew Lavinsky [MVP] Blog: http://azlav.umtblog.com Twitter: @alavinsky

  • 2012年6月1日 15:02
     
     

    Andrew, the data type for the actual or forecast start/finish is date field.  How can I set 'NA' to the field?  DateTime.MinValue?

    Thanks.