Is it possible connecting Project 2007 client to Project Server 2010?
-
2012年4月10日 20:44
I cannot connect to Project Server 2010 by using Project professional 2007. Does anybody know if its possible?
Thanks!
所有回覆
-
2012年4月10日 20:48
This is the error btw.
-
2012年4月11日 2:08版主
edmaisjm --The only way that you can connect Microsoft Project 2007 to Project Server 2010 is if your organization upgraded from Project Server 2007 and placed the Project Server 2010 install in Backwards Compatibility Mode (BCM). From the text of the error message, it appears your system is not running in BCM. Based on this, I believe you will need to upgrade to Microsoft Project Professional 2010 with all due haste. Hope this helps.Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"- 已標示為解答 edmaisjm 2012年4月11日 14:07
-
2012年4月11日 14:07
Thanks Dale!
I've installed a fresh version of Project Server 2010, so I'll have to install project professional 2010 too.
Thanks very much!
-
2012年4月12日 1:49版主edmaisjm --You are more than welcome for the help, my friend! :)