MS Project Professional 2010 and SharePoint 2010 Foundation - Project Tasks Synchronisation
-
2012年3月26日 12:43
Synchronisation of MS Project 2010 (Prof. Edition) with SharePoint 2010 (foundation) Project Tasks list fails with the following message.. (No MS Project server in this environment).
Invalid Predecessor
SharePoint only supports Finish-to-Start predecessors without constraints or lag times. Modify the affected predecessor and sync. again.
I would like to know if there is any workaround for the above issue, without having to modify the Project plan as per the above message. Thanks
所有回覆
-
2012年3月26日 16:16
Removal of Predecessor field in SharePoint helped synchronisation for now.- 已提議為解答 Anderson C. Oliveira 2013年4月9日 12:42
-
2012年4月3日 7:58版主
Hi svblr,
This feature works only for FS linkage as of now; you can refer to : http://blogs.msdn.com/b/project/archive/2009/10/19/project-2010-introducing-sync-to-sharepoint.aspx?PageIndex=2 also there is no Lag & Lead Support as of now.
Sapna S
- 已標示為解答 Sapna Shukla - Project MVPMVP, Moderator 2012年4月7日 4:36
-
2012年4月13日 14:00Thanks Sapna. I would also like to know if it's possible for the resources to enter the time spent (in hrs on a week) on a task in SharePoint 2010, so this can be synched with MS Project 2010.
-
2012年4月13日 14:19版主Yes it is possible, synch is 2-way communication between MS Project & SharePoint Site; resource updates can be synched back to MS Project 2010. There is a full video on this at : http://www.microsoft.com/project/en-us/demos.aspx titled SharePoint 2010 and Project Professional 2010.
Sapna S