  • HI, i am using DPM 2007 with Ultrium 3 library. detault inventory job runs at time of the backup running. any way to change the inventory job schedule, found job in SQL, changed the job times but didn't help.

    please suggest how to change the default inventory job timing.

    Mukul...

    2012年2月16日 上午 04:07

解答

  • i am able to solve this with the power shell..

      Set-MaintenanceJobStartTime [[-StartTime] <DateTime>] -DPMServerName <Strin
        g> -MaintenanceJob <HouseKeepingJobs> [<CommonParameters>]

    2012年2月16日 上午 06:41

所有回覆

  • i am able to solve this with the power shell..

      Set-MaintenanceJobStartTime [[-StartTime] <DateTime>] -DPMServerName <Strin
        g> -MaintenanceJob <HouseKeepingJobs> [<CommonParameters>]

    2012年2月16日 上午 06:41
  • Thanks Mukul, its working fine after change the time. previous sql job disabled automatically and created new sql job. 