Project Checkout Event handler
-
2012年4月2日 上午 07:37
Hi,
I had a requirement to catch Project Checkout event. Astonishingly, when I start writing code for the event I found that there's no event for Project Chckout. How am I suppose to catch event for Checkout (that is, if someone click on Edit button from PWA.)
Thanks,
Kashif
Thanks, Kashif
所有回覆
-
2012年4月25日 上午 08:54
Hi Kashif,
Agreed with you. Only way to find is the PSI where you can get the Project web service to find the project checkout/in status.
But you can hookinto your code in edit button on PWA. Here is a sample code with steps:If you can tell us the requirement, We can try to find the alternate way to do that.
Hope that helps.
Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82
-
2012年4月25日 下午 09:16
Thanks for the reply Amit, I've used that hooking up of button in for saving my custom web parts data. I should have tried this approach for Editing as well but it will only be effective for PWA, not for users using PP. Anyway its been a while now and I'd told the client its not possible for having an event for check out :)
Thanks again!
Thanks, Kashif
-
2012年4月26日 上午 05:19
No problem. I was away for a while so seems that I was late to reply your query.
Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82