Tasks do not display in task list in EPM

Unanswered Tasks do not display in task list in EPM

  • 2012年6月6日 下午 03:55
     
     

    Hi,

    One of the PM's in our PMO has 8 plans which are published with allocated resources. However, the resources are not able to see any of the allocated tasks by this specific PM in their tasks in EPM 2010. The PM has saved and published all his plans and has allocated enterprise resources from the resource pool, but the tasks allocated do not display.

    Thank you,

    Jaco


所有回覆

  • 2012年6月7日 上午 01:07
    版主
     
     
    Jaco --
     
    Ask the PM in question to display the Build Team dialog in each project.  By chance, is the Booking value for each resource set to Proposed?  If so, have the PM change the Booking value to Committed and then republish the project.  Let us know if this helps.

    Dale A. Howard [MVP]
    VP of Educational Services
    msProjectExperts
    http://www.msprojectexperts.com
    http://www.projectserverexperts.com
    "We write the books on Project Server"

  • 2012年6月7日 上午 06:22
     
     

    Hi Dale,

    Thank you for the feedback. I will test and revert back with an answer.

    Regards,

    Jaco