  • 2012年6月7日 上午 01:24
     
     

    Dear all,

    We want to keep the project in Project Center. And the project manager is not here.

    How to force - delete Tasks in My Work / Tasks for users? After delete, they will not see any deleted tasks (not strikethrough and wait to approve from Project manager)?

    Thanks all.

所有回覆

  • 2012年6月7日 上午 05:20
     
     已答覆

    Hi there--

    If your Project manager is not available & you want to remove the Tasks from team member's My task. There are two ways to do it
    1.An administartor of PWA, can Close tasks to update feature & once the PM is back She/he can iopen these tasks & delete/modify as desired. for mor einfo , Please see below article:
    http://technet.microsoft.com/en-us/library/gg597618.aspx
    2. Administrator or someone having permissions to open/edit the plan, can open the project in MS project & set the Publish field value as "No" for the desired tasks & publish the plan. If PM have already published a task and then later set the Publish field to No, when you publish the project again, the task will be removed from any assigned resources. for more info , please see below article:
    http://office.microsoft.com/en-us/project-help/publish-task-field-HA010167476.aspx

    Hope this helps.


    If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”. Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82

    • 已標示為解答 DoLeVu 2012年6月7日 上午 06:04
    •  
  • 2012年6月7日 上午 06:05
     
     

    Thanks very much, Amit.

    You help me a lot.

  • 2012年6月7日 上午 06:08
     
     

    You are more than welcome :) Glad to see that I was able to help you.


    If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”. Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82