Delete tasks in My Work / Task
-
2012年6月7日 上午 01:24
Dear all,
We want to keep the project in Project Center. And the project manager is not here.
How to force - delete Tasks in My Work / Tasks for users? After delete, they will not see any deleted tasks (not strikethrough and wait to approve from Project manager)?
Thanks all.
所有回覆
-
2012年6月7日 上午 05:20
Hi there--
If your Project manager is not available & you want to remove the Tasks from team member's My task. There are two ways to do it
1.An administartor of PWA, can Close tasks to update feature & once the PM is back She/he can iopen these tasks & delete/modify as desired. for mor einfo , Please see below article:
http://technet.microsoft.com/en-us/library/gg597618.aspx
2. Administrator or someone having permissions to open/edit the plan, can open the project in MS project & set the Publish field value as "No" for the desired tasks & publish the plan. If PM have already published a task and then later set the Publish field to No, when you publish the project again, the task will be removed from any assigned resources. for more info , please see below article:
http://office.microsoft.com/en-us/project-help/publish-task-field-HA010167476.aspxHope this helps.
If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”. Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82
- 已標示為解答 DoLeVu 2012年6月7日 上午 06:04
-
2012年6月7日 上午 06:05
Thanks very much, Amit.
You help me a lot.
-
2012年6月7日 上午 06:08
You are more than welcome :) Glad to see that I was able to help you.
If you found this post helpful, please “Vote as Helpful”. If it answered your question, please “Mark as Answer”. Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82