PWA CAN NOT CONNECT TO PROJECT SERVER????

Răspuns PWA CAN NOT CONNECT TO PROJECT SERVER????

  • 2012年5月4日 上午 11:42
     
     

    i am facing very serious problem,i installed the hot fix for microsoft project server (kb2596498) and after that my pwa site has stopped working.i do not have any idea why this has happened,i also tried to uninstall hotfix,but i didn't find any suitable method for it,when i am trying to open pwa site i am getting following error:

    Project web app can not connect to project server

    corelation id:204614b3-2c5c-4877b-a5d3-6d1caa6262af

    in the event viewer i am getting the following error

    Event7626(project server) of severity 'critical' occurred 20 more times(s) and was suppressed in event log

    event id is 2158

    if anyone has any idea ,plz help me

    

所有回覆

  • 2012年5月4日 上午 11:56
     
     提議的解答
    Hi Anuj,

    After the hot fix deployment , did you run the Sharepoint 2010 Products Configuration Wizard ?

    Thanks,

    Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82

  • 2012年5月4日 下午 12:00
     
     

    no i didnt.

    thanks

  • 2012年5月4日 下午 12:05
     
     

    is it essential to run the wizard??

    thanks

    anuj

  • 2012年5月4日 下午 01:44
     
     已答覆

    Hi Anuj--

    If you see the event viewer errors , You may find something:

    There is a compatibility range mismatch between the Web server and database "ProjectServer_Published", and connections to the data have been blocked to due to this incompatibility. This can happen when a content database has not been upgraded to be within the compatibility range of the Web server, or if the database has been upgraded to a higher level than the web server. The Web server and the database must be upgraded to the same version and build level to return to compatibility range"                                                     As far as I know, You'll need to run the SharePoint Products Configuration Wizard to complete the installation. To run the SharePoint Products Configuration Wizard, click Start, click All Programs, click Microsoft SharePoint 2010 Products, and then click SharePoint Products Configuration Wizard and complete the steps in the wizard.


    Thanks, Amit Khare |EPM Consultant| Blog: http://amitkhare82.blogspot.com http://www.linkedin.com/in/amitkhare82

    • 已標示為解答 anuj astro 2012年5月4日 下午 05:22
    •  
  • 2012年5月4日 下午 05:23
     
     

    thanx amit,my problem was solved by running the configuration wizard

    thanx again