Summary task not showing in project web app in schedule web part when a project plan is created from template RRS feed

  • Question

  • Hi All,

           I uploaded a project plan template and when a project is created on the basis of that template, it does not show/include the main summary task in the project plan, is it a default behavior of Project server or am i missing something here.

     

    Regards

    Adil Hussain

    Thursday, December 9, 2010 10:51 AM

Answers

  • assuming you are working on PS2010, and you are talking about "Project Summary Task" not showing up ? if yes, then while you open the Plan in PWA on the toolbar >> navigate to Options Tab >> under show / hide >> check "Project Summary Task"

    That should work :)


    Thanks | Sunil Kr Singh | http://epmxperts.wordpress.com