We are using Project Server 2007. We have a project where sometimes the hours in a resources task sheet is retained, and sometimes it disappears. We do not use timesheets. Updates are restricted to only PWA. Some of the resources that have
this happen are on multiple projects. Only their time for the one project disappears. I (administrator) have sat with both the resources and the PM during their process - only to have things work. For a while we were having issues with our
cube builing (after we installed SQL 2008 R2), but that issue has been resolved and this one lingers.
We are in the process of testing PS2010, but I'd like this problem resolved before we convert.
Our resources and PM are becoming very frustrated that I can't resolve this issue. Any help would be greatly appreciated.
Thanks,
Jean