Hi,
As Dale already answered that you cannot use project site calendar option to reflect in resource calendar. i would suggest to schedule this using your project schedule. create it as a task for your project resource, and assign resource to this task. it
would help you keep track of your resource engagements in details as well.
hope this helps.