Close tasks to update

Question
-
All replies
-
Closing tasks for update removes the tasks from the team member’s view in PWA and does not let the team member update the task. The task can still be reported on using the reporting database. They are stored in the same place as tasks that are not closed for update. I believe the property to filter on in the reporting database is MSP_EpmAssignment.AssignmentIsPublished.
Chris Boyd
Program Manager
Microsoft Project Team
-
-
Close tasks to update does *not* remove from the task sheet in PWA (you can only do this by unpublishing the task by setting Publish = No). It is still there, it just doesn't let the user update it. It appears with a little clipboard with lock indicator next to it in PWA.
Moreover there was a bug pre Feb 2010 CU that would give an error when a PM tried to set this property, even with the correct permissions.
The tasks and assignments that are closed to update are still in all the usual tables and views in all databases.
I don't see a field to report on this property in the Reporting database, but I believe the field in the Published database is MSP_ASSIGNMENTS.WASSN_LOCKDOWN_BY_MANAGER
Terrie T - MCTS - PMP - MBA****PMO & Project Server Admin- Proposed as answer by Terrie T - PMP-MCITP Tuesday, May 24, 2011 1:57 PM