locked
using MSPS 2003 need to add a completed task to a schedule RRS feed

  • Question

  • I have a task with resources that has already been completed, but was not included on the project schedule I need add this task to the existing schedule so the hours and resources are accounted for but need to know if there is any adverse reaction to doing this in PWA?
    Thursday, March 3, 2011 6:02 PM

Answers